Earthmoving Productivity Analytics: What to Measure and How
Earthmoving productivity analytics means comparing what your machines could move with what they actually moved, then finding out why the two numbers differ. The calculation is simple. The hard part is capturing clean data on cycles, trucks, idle time and quantities, and turning it into a daily decision instead of a month-end surprise. This guide gives you the formula, the metrics worth tracking, the data sources, and how a pilot-first AI approach, the kind we run at Digital Fractal in 90 days, connects it all for logistics, construction and oil and gas operators.
TL;DR
- Production per hour is load per cycle × (60 ÷ cycle time in minutes) × job efficiency. It gives you the potential, not the result.
- Track three layers: running time, working time and producing output (loads, cubic yards or cubic metres moved). Engine hours alone hide the gap.
- Truck availability usually decides real production. Analyze the loader and the haul fleet together.
- Real-time machine data can replace a 30 to 60 day accounting lag, as one Canadian contractor showed.
- An AI Readiness Audit ($2,500 to $10,000, one-off) maps which of these data streams you can use first.
Table of Contents
- The production formula behind every dashboard
- The metrics worth tracking
- Why the loader and the trucks must be analyzed together
- Where the data comes from
- From dashboards to decisions
- A practical starting plan
- What our approach adds
- Start with an audit
- FAQ
- Sources
The production formula behind every dashboard
Every earthmoving analytics tool rests on one equation. According to the HSM University CON-250 course, production per hour equals load per cycle × (60 ÷ cycle time in minutes) × job efficiency. Load per cycle is the heaped bucket capacity times a fill factor. The same course gives fill factors of 0.95 to 1.0 for loose sand and gravel, 0.8 to 0.9 for common earth and 0.6 to 0.75 for blasted rock. Job efficiency is commonly 0.83 (a 50-minute working hour), 0.67 in poor conditions and 0.92 in excellent ones.

Dirt in the ground takes up less room than dirt in a bucket or a truck. Loose volume converts to bank volume (the material in its original, undisturbed state) by dividing by 1 + swell. Swell is how much the material expands once dug. Bid quantities are normally in bank volume, so this conversion is what lets you compare production against the estimate.
A worked example
Take the example from the same HSM lesson: a mid-size excavator with a 2.0 m³ heaped bucket, a 0.90 fill factor, 25% swell and a 20-second cycle, working a 50-minute hour.
- Load per cycle: 2.0 × 0.90 = 1.8 m³ loose.
- Cycles per hour at 20 seconds: 3 per minute, so 150 in a 50-minute hour.
- Loose production: 1.8 × 150 = 270 m³/h.
- Bank production: 270 ÷ 1.25 = 216 m³/h.
The lesson stresses that this figure is only reached if trucks are always waiting to be loaded. That caveat is where analytics earns its keep.
What typical numbers look like
HSM puts mid-size excavator cycle times at 15 to 25 seconds. Swing angle, digging depth, material hardness, operator skill and truck positioning all move the number. Use published rates for planning only. Your own measured rates, by machine, material and crew, are the benchmark that matters once you have a few weeks of data.
The metrics worth tracking
Most contractors drown in metrics. For earthmoving, a short list covers nearly every decision.
Output metrics
- Loads and quantities: truck loads by equipment, cubic yards or cubic metres hauled, progress by area or phase. A 2023 MDPI protocol paper notes that earthmoving productivity can be derived from the volume of soil and rock moved per unit time, using the number of tipper-truck trips per day, with GPS-tracked laps from site to unloading point and back as the precision criterion.
- Production rate: units per machine hour and per crew hour, loads per truck per hour, compared with the bid rate.
- Daily production rate: total units completed divided by shifts worked, set against the planned rate.
Utilization metrics
- Equipment utilization: run hours divided by expected run hours. An excavator available for an eight-hour shift that works six hours is at 75%.
- Idle time: hours at idle divided by total hours. Idle burns fuel and adds wear without adding output.
- Running, working, producing: ignition-on time says a machine was exposed to work, not that it did any. Defining “working” by what the machine physically does (hydraulics under pressure on an excavator, blade engagement on a dozer) gives you a far more honest number than engine hours.
Cost metrics
Cost per cubic yard or cubic metre, with labor, fuel and maintenance tied to cost codes, is the number that connects the field to the bid. Compare actual unit costs with the estimate weekly, not at job close.
Why the loader and the trucks must be analyzed together
An excavator is rarely the bottleneck on its own. If trucks arrive late, the excavator waits and real production falls. The HSM lesson tells superintendents to watch for trucks queuing at the loader (too many trucks) or the loader sitting idle (too few) and to adjust the fleet daily.
That is a data problem as much as a field problem. To see it, you need timestamps for truck arrival, load start, load end and departure, plus the haul and return segments. Once you have them, you can answer questions that a daily production total cannot:
- How long does a truck wait at the loader, on average, by hour of day?
- Which haul segment varies most from cycle to cycle?
- Does production drop when a specific truck count is reached, or only when a specific road section degrades?
For logistics firms running dispatch alongside earthworks, this is the same queueing logic you already apply to yard and dock operations.
Where the data comes from
You have four practical data sources, and most fleets end up combining them.
Machine telematics and machine control
Onboard devices report location, engine hours, idle time, fuel and, on newer machines, bucket and blade activity. Canadian contractor ASL pushes machine-control data from the field to the office through the cloud, into internal databases, Microsoft Power BI and vendor dashboards. According to Heavy Equipment Guide Canada, this replaced a 30 to 60 day accounting lag, so managers now know within seconds if work is being done incorrectly, which improves bidding accuracy and schedule control.
At scale, the same approach changes habits. Ottawa-based R.W. Tomlinson reports more than 700 machines feeding a cloud telematics platform that monitors utilization, idle time, fuel use and site-wide productivity. At its quarries, daily safety meetings start with operators reviewing utilization and idle dashboards, and crews compete across sites for the lowest idle time, per the September 2025 Heavy Equipment Guide Canada report.

Low-cost GPS
You do not need a premium sensor stack to start. A 2018 case study of a basement excavation at Concordia University in Montreal combined GPS data with fuzzy set theory and estimated onsite productivity at 226.63 bank m³/h, against 230.5 bank m³/h measured by the contractor. The GPS unit cost 370 Canadian dollars, with a storage server of about 50 Canadian dollars a month. The authors argue the method is affordable for small and medium contractors.
Added sensors
Another Concordia study built near-real-time models using GPS, accelerometers and load cells with a gateway and database. In field work in Saint-Laurent, Quebec, it recognized truck states across 15 simulated cycles and detected road bumps with 83.3% accuracy and potholes with 82.6%. The thesis argues that measuring productivity alone is not enough: you also need to identify the problems and causes behind it, such as poor haul road surfaces.
Site cameras and computer vision
Sensors get expensive across a large, mixed fleet. A Concordia computer-vision framework uses three neural networks to detect, track and recognize the activities of multiple excavators from site cameras. On real site video it reached 87.6% activity-recognition accuracy and 83% productivity-calculation accuracy, and it identified excavator-truck workgroups to diagnose why machines idle. A peer-reviewed review of 119 papers on automated earthmoving monitoring compares vision and sensor methods and notes that manual monitoring is labor-intensive and inefficient. If cameras are already on your sites, our page on AI video analytics for construction shows how that footage becomes measurable activity.
From dashboards to decisions
A dashboard that shows last week is a report. Analytics pays off when it changes what happens tomorrow morning.
Spot delays while they are happening
Compare planned and actual production by shift, not by month. When a haul crew falls behind the bid rate, you want to know that day, with the reason attached: long truck wait, long swing angles, a soft haul road, a late fuel stop. Edge processing helps when sites have poor connectivity, because data is analyzed near the machine and only the results travel. We cover that in our guide to edge IoT analytics for real-time control.
Redeploy underused assets
Utilization data shows machines that sit. In a Canadian rental example, Stephenson’s Rental Services in Mississauga uses run-hour data to schedule preventive maintenance and uses utilization data to tell customers they may need three machines instead of four. The same logic applies to your own fleet: low utilization on one site and queueing on another is a redeployment decision. Run-hour trends also feed predictive maintenance for contractors, so a machine is serviced before it fails mid-shift.
Forecast instead of reacting
Traditional forecasts lean on previous projects and a project manager’s judgment. A University of Alberta-led study in the Journal of Management in Engineering combined machine learning with time-series analysis, using daily report logs and weather to forecast equipment productivity. Over an eight-month excavation case, the model reached an R² of 0.89 against 0.71 for a classical model and cut estimation error by 63% compared with the project manager’s approach. The Canadian Construction Association’s June 2022 insight report says real-time analysis of data could increase construction productivity by 50 per cent, citing a case where big data technologies cut work times by that amount.
Keep the office and the field on one record
The value disappears if machine data, 3D models and cost codes live in separate systems. For a view on how cloud construction platforms tie field data to office reporting, see this guide to cloud workflows for field and office data. Our workflow automation and API integrations work is about the same goal: one pipeline from the machine to the report.
A practical starting plan
You do not need to instrument every machine to learn something useful. A staged approach keeps the cost low and the learning fast.
- Pick one spoil-and-haul operation. Choose a loader and its trucks on a single job with a known bid quantity.
- Define “working” and “producing.” Write down what each machine type must be doing to count, and what unit of output you will record (loads, bank volume).
- Capture cycle and wait timestamps. Use whatever you already have: telematics, GPS on trucks, or site cameras.
- Compute potential versus actual. Run the formula above with your own fill factors and swell, then compare it with surveyed or counted volumes.
- Review weekly against the estimate. Look at unit cost per cubic yard or metre, idle percentage and truck wait, and change the truck count or haul route.
- Scale only what moved the number. Add machines, sites or automation where the first pilot showed a measurable gain.
What our approach adds
Most earthmoving operators already own some of this data and use almost none of it. Our AI Readiness Audit starts by finding which data you hold, which decisions it could drive, and where automation would save the most time. From there we build tailored solutions around your workflows, systems and goals, aimed at tangible results within 90 days. For construction operations, our automation use cases that deliver ROI show the kind of repetitive reporting and dispatching work we target.
Our view
Productivity analytics fails when it starts with a tool. It works when it starts with a decision: add a truck, move a machine, fix a haul road, re-bid a rate. We design for the decision first, then work back to the data it needs.
The pattern we recommend is pilot-first. Pick one operation, define what “producing” means for each machine, and get the measurement right before you scale. That is why our work is tailored to each client’s workflows and systems rather than a generic package, and why we aim for visible change inside 90 days.
For logistics firms and contractors alike, the real prize is closing the gap between the number a machine could produce and the number it did, every shift, with the reason attached. The research shows it is achievable with modest hardware, cameras or existing telematics. What takes skill is joining those streams into something an operator and a superintendent will actually act on.
Souhail
Start with an audit
If you want to know which of your sites, machines and data feeds can support productivity analytics first, our AI Readiness Audit is the place to begin. It is a one-off engagement priced from $2,500 to $10,000, and it identifies where automation and AI will pay off in your operation, including construction and logistics. From the audit, we can move into AI implementation and build-out built around your own fleet and workflows.
FAQ
How do you calculate excavator productivity per hour?
Multiply the load per cycle (heaped bucket capacity × fill factor) by the number of cycles per hour (60 ÷ cycle time in minutes), then by job efficiency. Divide the loose result by 1 + swell to get bank volume. In the HSM University example, a 2.0 m³ bucket with a 20-second cycle gives about 270 loose m³/h, or about 216 bank m³/h.
What is the difference between utilization and productivity?
Utilization measures how much of the available time a machine spent working, for example run hours divided by expected run hours. Productivity measures what it produced in that time, such as loads or cubic yards per hour. A machine can be highly utilized and still unproductive if it waits for trucks, so you need both numbers.
What data do I need to start?
Start with machine hours, idle time, truck loads and the quantities moved, ideally with timestamps for loading and hauling. Add surveyed or drone-measured volumes to check your counts against reality. Telematics, GPS units or site cameras can all supply the cycle data.
Can small contractors afford this?
Yes, at a starting scale. The Montreal case study used a GPS unit costing 370 Canadian dollars and a server at about 50 Canadian dollars a month, and still estimated productivity within a few percent of the contractor’s own measurement. Starting with one operation keeps the cost proportionate.
Sources
- Equipment productivity and cost, CON-250 Lesson 11, HSM University
- Protocol Proposal for Data Collection and Processing in Earthmoving (MDPI, 2023)
- Automation of Measuring Actual Productivity of Earthwork (MDPI, 2018)
- Automated Productivity Models for Earthmoving Operations (Concordia University)
- Computer Vision Based Automated Monitoring and Analysis (Concordia University)
- Critical Review and Road Map of Automated Methods for Earthmoving Productivity Monitoring
- Data-driven construction saves Canadian contractor time (Heavy Equipment Guide)
- How one Canadian contractor turns data into decisions (Heavy Equipment Guide)
- Stephenson’s Rental Services Optimizes Fleet
- Forecasting Construction Equipment Productivity (Journal of Management in Engineering)
- Insight report: Innovation & R&D in construction (Canadian Construction Association)
- Cloud workflows for field and office data